Update on Construction – 4/23/20

This afternoon construction crews finished asphalt patches on two manholes in Grant Ranch Boulevard between Grant Ranch Elementary and Sunset Park. They were trying to get those two manholes done Friday/Saturday last week but ran into some issues with the excavation walls sloughing on the one in front of Knowledge Beginnings.  The base was poured on that one Saturday and finished building it today.  Crews were still able to stack the rest of the manhole, back fill , and asphalt patch back today.

Crews will be back next Monday to finish the last three manholes, one near Sunset Park in Grant Ranch Boulevard, one in the Belvedere neighborhood, and one in the Promenade neighborhood.  Should be able to finish that up next week.

2020 Capital Improvement Preliminary Construction Schedule

Mobilization
Duration – 3 days
3/16/20 – 3/18/20

Sumac Removal and Replacement
Duration – 10 days
3/16/20 – 3/27/20

Underdrain Manhole Installation – Grant Ranch Blvd
Duration – 10 days
3/23/20 – 4/3/20

Underdrain Manhole Installation – Residential Neighborhoods, Belvedere and Promenade
Duration – 10 days
3/30/20 – 4/10/20

This schedule is subject to change and is dependent on any restrictions put in place related to the COVID-19 (Coronavirus) situation.  Work crews will close and clean up the site nightly to minimize disruption should they not be able to return the next day.